Removal of unloading arm at Haldia Terminal

Removal of unloading arm at Haldia Terminal
  • Project location – Haldia Oil Jetty 3
  • Client – Reliance
  • Project description – Dismantling and removal of unloading arm from service jetty in 3 parts (swivel, arm with counter-weight and riser) and subsequent loading onto trailer and delivery at RIL yard
  • Technical details and constraints
    • Unloading arm – Max. Weight of LA1 part : 24 T
    • Barge arrangement – M.V. Joysagar (60mX15m) with Tug Ghatotkach (1042 HP)
    • Crane – 100 T capacity (24 T load capacity at 16 m radius ,boom 35 m)
    • Working condition – Currents : 3 knots, Wave height : upto 1.0 m
  • Logistics and operational details
    • Total time of operation – 4 days
    • Jetty downtime – 6 hours per day X 2 days

Leave a Comment

Your email address will not be published. Required fields are marked *

Phone: +91-33-243-5382/5384
Fax: +91-33-248 8182
9/12, Lal Bazar Street, Kolkata - 700001, India
Mercantile Buildings, 2nd Floor

Powered by themekiller.com anime4online.com animextoon.com